CHALLENGE
Petroleum Coke Facility Stacker/Reclaimer Track Stabilization (2020- 2021) 1,800 foot long track that supports stacker/reclaimer equipment weighting about 1.5 million pounds and material conveyor belt. Constructed in 1969 with crane rail supported on 32 foot long prestressed concrete ties spaced on 10 foot centers with three 8 foot long ties beneath each rail between the long ties. Only localized tie and subgrade maintenance had been performed in the 50 years since construction. Some locations in the track were significantly outside of the track grade profile (elevation difference between fixed points along one rail) and cross-level (elevation difference between rails) tolerances for the stacker/reclaimer operation.
SOLUTION
Purpose of the compaction grouting project was to restore stabilize the deteriorated subgrade beneath the track and bring the track to within new construction tolerances of +/-1/4 inch crosslevel and 1:400 (1 inch vertical in 33.33 feet horizontal) for grade and profile.
PROJECT SUMMARY
Stabilized the triple barrel box culvert and soils Project began September 2020 and was complet- ed April 2021 with approximately 3 week break in December 2020.
1376 locations were drilled and grouted using 11,925 cubic feet (442 cubic yards) of grout material.
Grout pattern was 1 vertical and 1 diagonal underneath each rail of the long ties and 2 verticals under each rail of the center short tie.
Project completed two years ahead of schedule.
Superior Grouting is a top choice for various grouting services in Houston, the entire Gulf Coast Region, and the areas nearby. It holds more than 35 years of experience in the grouting industry. Also, Superior Grouting is known for using the best tools and state-of-the-art equipment in providing clients with the best results.
Copyright © All rights reserved. 2024 • Terms of Use and Privacy Policy • Internet Marketing by Authority Solutions®